Panel Installation

By |December 9th, 2015|BODY BUILD|0 Comments

With the chassis low and right next to the router it was reasonably easy to lift the panel into position. We started with the left panel, which was the other side of the router and the second panel only needed standing up from the router bed straight into position.

Both panels are hanging on the lifts and get glued to the chassis frame.

 

 

Cutting the panels

By |December 9th, 2015|BODY BUILD|0 Comments

Since I had everything in CAD it was fairly easy to transfer the files for the cut outs to the software Vanglass uses for the router. The cut outs stay attached at a few stops for stability of the panel during cutting and it is also a good concept to leave everything in for the way home. I only needed to tape up the gaps.

The large panels needed about an hour and a half to be cut.

 

 

The side panels had a rebate at the top and front for better and stronger connection to the roof and […]

Preparing for the panels

By |December 9th, 2015|BODY BUILD|0 Comments

The plan was to mount the body in the factory because the panels are way too big to be shipped and it would be a pain without the proper tools and more so without the experience of the guys at Vanglass.

Unlike the US vans this one is not as high, still the panel is 3m high and over 11m long. Than van is 2.8m at its highest point and we needed all the height of the lifting gear to get the panels on.

The first thing in the factory was to remove the wheels and drop it down as low […]

New Tyres

By |December 8th, 2015|BODY BUILD|0 Comments

 

The Nullarbor on 2 trailer wheels was no problem. The Duramax ticked over nicely, hardly working with a light tail wind. At 100kph the engine revs at 1600 and I did not even use tow mode. Form Madura to Ceduna I used under 14l/100km. In Ceduna I mounted the new tyres on the trailer and went on to Peterborough where I spent the night.

A nice coffee shop in the old cinema makes an interesting place for a break.

 

 

After Peterborough the roads got worse and worse. Past Broken Hill and the rest on NSW was atrocious. I was happy to […]

Burning Rubber

By |December 8th, 2015|BODY BUILD|0 Comments

The trip over to QLD started ok until I reached the Nullarbor with an outside temperature of 50 degrees. I had different tyres on the truck and the trailer, old tyres I have to admit. I did not want to ruin my new set of 12 because I knew that the alignment of the front of my truck was off and that the tyres would not last much more than the trip. I thought the trailer tyres, also an old set, might last the trip, however it was not to be. Just past Madura, actually before the Nullarbor on […]

Ready To Go

By |October 16th, 2015|BODY BUILD|0 Comments

All packed up. Antennas and radios are back on and in the truck. I had the HF antenna removed when I needed to get on a friends hoist and had not put it back. Now its worth for the trip. Can do some DX calls from the Nullabor plain.

I also have the UHF/VHF radio back in again with the GPS for the APRS system. The 2m whip is on the left in the picture. The whip on the right is the long whip which can go on top of the HF antenna instead of the short whip with the […]

Ready For The Body

By |October 14th, 2015|CHASSIS BUILD|0 Comments

The last few days I finished the floor and prepared the chassis for the trip to QLD. I still had a very small leak in the airline around the load share valve, but it is now fixed. I also connected a few more cables to the load share valves and the brake locks.

Shaun was so kind to organise the glue for me. Sausages of 600g with KD Bond. Of course a German product for the Teutanic.

I used an air gun to apply the glue. For the whole floor I used 13 of the sausages, which makes another 7+ kg.

The […]

Load Share Air Line

By |October 7th, 2015|CHASSIS BUILD|0 Comments

Today I connected the load share valve for the air line between the two airbags on each side. After it was done and working I tested the suspension and timed the pressure equalisation between the bags and discovered that it was simply not sufficient. The valves I had used restricted the flow too much and so did the 3/8 plastic tube. Not good.

The load share between the bags is a valuable feature especially on rough roads. I also want to study the suspension characteristics with and without load sharing and in order to do that I need to make […]

Measuring

By |October 7th, 2015|BODY BUILD|0 Comments

This is the first post in the category “Body Build”. The day gets closer when I leave to QLD for the body to go on. One of the main activities the last three days was double checking measurements. The paper specifications of the windows, doors and baggage doors are all 5-10mm wider than the actual cut-out needs to be.

I was wondering about that but from the answers I got from the manufacturers of the items it is just for fitting purposes. All these items are custom made to measure and are not mass produced with a fixed size. The […]

Overdue Update

By |September 30th, 2015|CHASSIS BUILD, COMPONENT BUILD|0 Comments

If you read this on facebook you are missing 11 images. Only the website has all the images in a post.

Ten days now since I posted last. Lot’s of things were happening including some rubbish removal and clean up, electronic work, many little things on the chassis, my commercial project, some kite surfing, fitted the exhaust of the truck again  and some more shopping for parts.

More than 20 years of my IT history went into the rubbish. A shame really, all still working but nobody would use a 21″ tube screen anymore. I also dumped my NeXT computers, […]

IT IS DONE – Finished Welding

By |September 20th, 2015|CHASSIS BUILD|2 Comments

Last three days were busy with finishing all the little bits of the frame and TIG welding them together. Yesterday I finished the last pieces and then my mate MIG welded the riveted frame components to the thicker chassis pieces.

The outriggers in the front were welded to the neck frame.

The front panel support rail is fitted.

All the frame components for the underbelly cover are fitted and welded.

It is handy to have the strong hydraulic legs to lift the chassis. Easy access from underneath, however the manufacturer recommends not to use them for changing tyres. We should have used axle […]

Underfloor Storage Frame Finished

By |September 16th, 2015|CHASSIS BUILD|0 Comments

well almost.  Just a few bits left on the rear right. I also added a few of the underbelly cover supports. These are t-sections across the underside of the trailer. These will be used to hold the cover sheets of alu honeycomb 6mm panels. These panels will cover the whole underside from front to rear.

I have to do a few more of these tomorrow and then the lot will be welded. In the middle section is a bit more to do because the trailing arms require a bit extra work to go around them and cover everything else.  I […]

Underfloor Frame Welded

By |September 15th, 2015|CHASSIS BUILD|0 Comments

Today I continued with the underfloor frame in the front and on the right side.  The front is finished and the right side is half done.

In the afternoon a mate came by and helped me with the welding.

All the frames, which are finished so far, are now welded together. We used the TIG welder for all the 3mm to 3mm alu.

The connection between the frame and the thick chassis components will be done with the MIG welder.

As it looks right now I will be finished with all the frames and the supports for the underbelly cover by Saturday evening, […]

Under Floor Frame Continued ..

By |September 14th, 2015|CHASSIS BUILD|0 Comments

Today I continued with the frame in the front left of the chassis. Takes a while, pretty fiddly to get this nice and straight.

I have checked some measurements from the plan and took some baggage doors to the chassis to double check positions. My wife and I and a bit of a discussion about pull out table in the front, table height, pass through shelf to the kitchen and door position and a couple of other things.

Looked a seating height with the pull out table outside, opening direction of the door and the placement of the door. I am […]

Under Floor Frame

By |September 13th, 2015|CHASSIS BUILD|0 Comments

After two days of work on my commercial project and rain yesterday, the weather was better today and I done some work on the trailer again.

I did do some more programming for the BMS, which is now almost done. Need a couple of parts and need to put it in a box.

Outside I started the work on the last chapter of the chassis build, the under floor frame for the storage boxes and the underbelly cover.

I also have finished all cutting for the outriggers and side rail for the neck section. The pieces are waiting to be welded.

I tried […]

It is on again – Start of the kite season

By |September 9th, 2015|CHASSIS BUILD|0 Comments

at least for me .. Some of my kite friends have been out all winter but this winter was really not very nice in terms of kiting opportunities.

This was the first time I was out in some time, and unfortunately it was not that great. Beautiful day at the beach, nice water, but just not enough wind and I did not pack the big gun. I trusted the actual reading too much and it dropped as per forecast. The boys at the bureau got it right this time and I did not believe them. Tough luck .. next time […]

Holding Tank Plumbing

By |September 7th, 2015|CHASSIS BUILD|0 Comments

Today was a real warm spring day, the first taste of what is to come now – kite season. We had a seabreeze, just right for a big kite, but I was busy .. Wednesday looking good though although the forecast says otherwise, but our seabreezes never listen to the forecast.  Back to the subject – plumbing.

I finished the cold water and drinking water plumbing, the hot water was already done. After the water supply was no finished, the holding tanks were the next on list.

I placed the shower basin in it’s spot to check the drain, I had […]

Hot Water Plumbing

By |September 4th, 2015|CHASSIS BUILD|0 Comments

After I finished the data entry for the BMS I went outside to do some more plumbing. Yesterday evening I had picked up some more insulation for the hot water pipes as one can see in the top picture.

I looked at the possible routes for the pipes and decided that some of the fill lines were in the way. I removed them to get a better route for the hot water.

I use cable tie saddles to fix the pipes to the chassis.

The saddles are riveted to the floor supports with pop rivets.

In the foreground one can see the hot […]

Hot Water Plumbing

By |September 3rd, 2015|CHASSIS BUILD|0 Comments

As I mentioned before, I went against my initial thought and decided to use PEX with crimp fittings for the hot water and heating pipes. Today I started putting the hot water pipe in and done a few fittings with the crimp rings. Looks very solid and I think I am going to trust that. Cutting the PEX pipe is easy with a dedicated cutter, very clean ends and the crimping with the ratchet tool is simple.

I used the PEX pipe from the roll, which can be a bit daunting, but buying straight pieces would not really helped the […]

Holding Tank Valve

By |August 30th, 2015|CHASSIS BUILD|0 Comments

Not getting ahead really well at the moment. The plumbing is not my strong side and it gets a bit boring, however it gotta be done. Today I had to take a step back before I could make a few small steps forward again.

I had to relocate the rear holding tanks. It is a real pity since they were sitting very nicely, however they were too high and there was not enough space between the top of the tanks and the floor. I did not want the inlets going into the side, I want them straight in from the […]