CHASSIS BUILD

Brake Actuator

By |May 20th, 2015|CHASSIS BUILD|0 Comments

Lots of things happening … including a car accident .. some puppet had to push 4 cars into each other and I was the front one. Had our little city car and the poor thing is now in car hospital. I am ok, no problem, just very annoying. When do they learn to drive in Australia?

Anyway .. back to the subject ..

The electric over hydraulic brake actuator is mounted in the front of the lower chassis.

Mounts for the rear holding tanks are in, the middle section between the two tanks is not yet done.
All the floor supports are done […]

Main Chassis Frame Welding Almost Finished

By |May 18th, 2015|CHASSIS BUILD|0 Comments

Done some more welding today. The rest of the main chassis welds were finished and the first welds done for the thinner alu, like the floor supports and some tank hangers.
Have fitted the first leg as a test.

All the steel parts are at the powder coaters and I expect them to be ready by Thursday. During the week I have to organise lots of little things. Next Friday we plan to put the wheels on and pull the lower chassis out of the shed to mount the neck.

I have some 6mm channel in 6082 which I will cut to an angle to […]

Mounting Suspension Hangers

By |May 16th, 2015|CHASSIS BUILD|0 Comments

Two very busy days, yesterday and today.
Done lots. Finished all alu welding on underside and all steel welding.
First time I had all suspension hangers mounted to fit the trailing arms.

Above shows all 4 trailing arms mounted for alignment and tacking on the blocks.

Above shows a wheel from behind. Have sorted out the routing of the flexible brake line and the bracket mount on the trailing arm to securely fix the brake line. Made little plates and welded them onto the trailing arm.

Finished the bumper mounts. Sacrificial bumper and mounts. If someone bumps into us it will take some of the […]

Coupling Brace

By |May 9th, 2015|CHASSIS BUILD|0 Comments

These 4 and 4 more were the last bits I had from cutting the 5 9.9m RHS main rail sections. They are now the rear mounts for the bumper and the the other 4 are gussets for the cross member which holds the angles from the coupling braces. I have nothing left from those long sections, just a few shavings.

 Fitted the coupling braces to day and tacked them. The last bit of steel welding. Tomorrow I will continue cleaning the parts from splatter, like I started today to get them ready for powder coating. Pretty heavy now that coupling bit. […]

Coupling Welding

By |May 8th, 2015|CHASSIS BUILD|0 Comments

Another busy day over.
My laser cutter did let me down a bit and did not finish a couple of parts I wanted to use this weekend.
Anyway, my mate was here again and we almost finished all the steel works. Trailing arms are done, the shock mounts on the trailing arms as well as on the chassis, two of the airbag platforms, waiting for a couple of parts for the other 2 airbag platforms to finish.

Above is a pic of the outer coupling tube. The actual coupling slides into this tube. Obviously this is upside down since the neck still lays on the […]

Flange Gusset

By |May 2nd, 2015|CHASSIS BUILD|0 Comments

Above is the image of the flange gussets I was talking about. Not cleaned up yet, just shown as welded.

Steel Welding

By |May 1st, 2015|CHASSIS BUILD|0 Comments

Done steel welding today.
Tacked and fully welded all trailing arms and started the coupling mount. Checked the wheel position and clearance as well as calculated overall width. Above image shows one wheel mounted on a trailing arm with the center cap. The wheel liner (stainless) is not on the wheel, so it is a bit ugly. Outside center cap left to right is 2480mm. Without center caps its is 2420mm from tyre face to tyre face.

The trailing arm distance from the inside face of the flange ended up 1mm out from the  original design. I am pretty happy with that. The reason was in […]

Welding The Neck Section

By |April 26th, 2015|CHASSIS BUILD|0 Comments

Was a good day today. Finished welding of the neck. It sits on top of the lower chassis upside down.
Very sturdy, massive gusset hold it together in all directions, will have very little twist.

Below is one trailing arm sitting on a suspension hanger. Waiting for the part, which is redone, until I can fit
the last cross member. Looks all good though. All measurements are spot on and everything is very much like it is designed.
We have under 1 mm deviations from the planned measurements, which is amazing considering how alu pulls in when you fully weld it.

Below is a pic […]

More Welding

By |April 24th, 2015|CHASSIS BUILD|0 Comments

Yesterday and today I was working on the chassis.
The rubber membrane for the separation of the steel suspension hangers from the alu mount plate has arrived.
The neck SHS is back from my machinist with all the holes drilled.

I have tacked up some cross members and work on fitting the suspension hangers but have to do a slight modification. Not enough clearance for the 1.5mm membrane. The last version of the new counter plate (I had that redone) is still no good. I was sloppy in calculating the total width and forgot to take one layer of membrane into account. I did not […]

Welding Chassis Frame

By |April 17th, 2015|CHASSIS BUILD|0 Comments

Busy day, had a few beers after work and got too late for pics.. was dark by then.
The suspension hangers are welded up, no problem at all .. no bending – easy
The trailing arms are tacked, the axle sleeves are welded to the hub adaptors and we
put the the outer cross members on the chassis after we did set it on the saw horses
and got it level. That took actually only a few minutes, totally surprising, once we had
the main rails on the saw horses and just eye balled the levels and direction and the measured it with the laser […]

Cutting Steel Parts

By |April 16th, 2015|CHASSIS BUILD|0 Comments

Today I did cut all my steel parts for the trailing arms.
I prepared the steel parts we intend to weld tomorrow including the suspension hanger plates.
Above is an image showing all 4 suspension hanger plates lined up through a 1.5″ steel rod to keep them perfectly aligned when we weld.

The mounting blocks for the trailing arms will be pressed between the hanger sides with a couple of blades from a feeler gauge to give it just a tiny bit of play(0.05mm) and more importantly all the same. The hanger plate is 8mm steel and will be bolted to a 10mm alu plate […]

Second Chassis Rail

By |April 11th, 2015|CHASSIS BUILD|0 Comments

Today we finished the second main chassis rail.
Went really well and was good working in pleasant conditions, a bit rain once in a while but nice temperature.

After finishing the main rail we started the neck section.
The two side pieces first.

Tacked up to keep them nicely symmetric and then fully welded on both sides to keep them aligned. If one side should pull in a bit the other would follow.
The heat and the smallest of gaps can distort a perfectly aligned angle.

Massive brace under the neck will hold everything together.

 

Chassis Rail Finished

By |April 10th, 2015|CHASSIS BUILD|0 Comments

We have finished one rail 8650mm long and 5.80m at 9″ high and 2.85 at 12″ high.
Massive beam, which is calculated to carry 5.5t at a required strength of 1/6th of the yield strength of the material.
The whole trailer is calculated at 6t maximum capacity at off road standards.

We will do the second rail tomorrow.

I also received another bunch of Visduinos today from China and am doing a few more compatibility tests.
The Visduinos appear to be better than some of the Arduino clones I got from an Australian seller (most likely also from China).

The First Weld

By |April 10th, 2015|CHASSIS BUILD|0 Comments

Today (10-4) welding started in earnest. First step was tacking the main rail and the sub rail carefully from both sides. We marked the intended welds, staggered on both sides with some gaps and the tacked the two pieces carefully to keep them straight. Not paying attention to evenly spread the welds, and not too close in the beginning, might result in a banana shape. It is quite amazing when you see how this big beam can bend by just misplacing a couple of welds.

The main rail is 9″ high with a long section behind the suspension of 12 […]

Ready For Welding

By |April 9th, 2015|CHASSIS BUILD|0 Comments

All the pieces are cut and the shed is ready to start welding tomorrow. My mate is coming in the morning and we will start putting it all together. Will be interesting.

So finally it is going to happen and the actual build commences.

 

Suspension Hanger

By |April 9th, 2015|CHASSIS BUILD|0 Comments

Little gussets, the main alu plates (10mm) for hanging the suspension mount, the newly made counter plates in 6mm (they fit perfect now) and the components for the coupling mount. Those big pieces at the right top are the two braces for the coupling mount. The neck itself is with my machinist at the moment and gets a few more holes. 4.5″ square steel 1/4″ thick is nothing
you work on with an amateur drill stand. I also have bought the stainless steel bolts, mudguard washers and lock nuts to fit the suspension mounts and the coupling mount. The coupling […]

Cutting Material

By |March 28th, 2015|CHASSIS BUILD|0 Comments

I made a bit of progress in several areas.
Cutting is going quite ok, have done the two beams with the most cuts. Two more with only a couple of cuts, because they are the main ones, and one more mixed length one.
The number of puzzle pieces is growing. We will start welding on the weekend after the next long one.

The picture below show the cut off of beam two. This is about the average cut off. Less then 10cm from a total of 49.5m.

Rear Deck – Thoughts

By |March 28th, 2015|CHASSIS BUILD|0 Comments

We had a discussion about the rear deck again and have decided that we want the deck but not the sky-deck from Melbourne for several reasons. One is price of course. 15k is over the top, but more importantly it has a design problem.
After looking closely and making a few calculations, and also some statements from the conversation on the phone made me sceptical. I was told that the sky-deck does not like a twisting body at all and that internal stiffening is important.
This made me think. The fact that the sky deck has only the support from the roof end […]

The First Cut

By |March 25th, 2015|CHASSIS BUILD|0 Comments

Today I adjusted the saw to a perfect 90 degree angle to the blade to make sure that I have very nice right angle cuts. I used one of the machined mounting blocks which I have from my machinist for the trailing arm hanger. These blocks are absolutely perfectly square and ideal for the job.

Having done that I realised that this angle is ok to adjust without additional tools but the other problem is the vertical angle. Over a length of 9m a minimal angle away from a perfect horizontal level will result in a not so perfect vertical […]

Solar Panels Arrived

I added a couple of pages to the website.
One about the 240V system and one about my first cut with a little video of the saw in action.

I have adjusted the saw perfectly square and will get a laser level tomorrow for the vertical adjustment.

The solar panels came today, so now all my components for the 240V system are here, the batteries, inverter/charger,
solar charge controller and flexible solar panels.

The cables on the solar panels are pretty long, I will have to shorten them in groups of 4 because the panels will be rather close and I don’t like the long […]